In IJmuiden, located at the mouth of the 27 km long Noordzeekanaal that links Amsterdam and its port with the sea, the Ministry of infrastructure and the Environment is building the world's largest sea lock. The extremely tight construction site and the tight schedule add to the complexity of the project. The gates in the new lock will reach almost 8 m above the current water level, thus providing defence against rising sea levels. The enormous lock will be made out of 290 000 m3 of concrete.
64
thema
World's largest
sea lock
1
Noordersluis in IJmuiden replaced
by a new gigantic concrete lock
In IJmuiden, located at the mouth of the 27 km long Noordzee-
kanaal that links Amsterdam and its port with the sea (fig. 1),
the Ministry of infrastructure and the Environment is building the
world's largest sea lock. The extremely tight construction site and
the tight schedule add to the complexity of the project. The gates
in the new lock will reach almost 8 m above the current water level,
thus providing defence against rising sea levels. The enormous
lock will be made out of 290 000 m
3 of concrete.
IJmuiden has a long history as gateway to the Noordzeekanaal
for sea going vessels. In 1876, the Noordzeekanaal was opened
with the still operational Kleine sluis (Small lock) and
Zuidersluis (Southern lock). The rapid development in the
early years was crowned by the opening of the Middensluis at
the end of the 19th century. At that time the Middensluis was
the largest lock in the world. The construction of the Noor -
dersluis in 1929 completed the lock complex in IJmuiden. With
a length of 400 m, width of 50 m and depth of 15 m it became
the largest lock in the world then.
Replacement of the Noordersluis is necessary after being in use
for nearly a century. A new and larger lock should improve
thema
World?s largest sea lock 3 2017
65
accessibility to the port of Amsterdam and strengthen the
economy of the region by offering a tidal independent access
for vessels constantly increasing in size. The new lock will be
70 m wide, 500 m long and 18 m deep (a typical cross section is
shown in fig. 3). This lock will be the largest in the world and is
situated just in between the existing Noordersluis and Midden-
sluis, which are two locks currently in use (fig. 2). Continuous
operation of these locks has to be guaranteed during construction
of the new lock, thus requiring numerous considerations for the
impact of construction on the existing locks.
The lock complex, besides having the obvious navigation facili-
ties, features multiple other functions. A key feature is the
primary flood defence. Water management (management of
the North Sea Canal), passing road- and water traffic and
environmental objectives (fish migration) complete the main
functionalities of the new lock.
The walls of the new lock are primarily constructed as anchored
diaphragm walls. The execution of this type of structure has a lot
of advantages compared to the execution of steel combi-wall or
sheet pile walls with respect to (sound) nuisance and vibrations
which could influence the stability of the existing locks and of
the primary flood defence.
The new locks will be provided with rolling steel gates that are
parked in a gate chamber when the gate is in open position.
The seaside upper lock head will have one gate chamber. The
lower lock head will have two chambers, one for the operational
gate and an additional chamber for a spare gate. The concrete
structures holding the gate chambers have an area of 80 × 26 m
2
and 80 × 55 m
2 and a height of 30 m.
The contract for the design, construction, finance and mainte-
nance during 26 years was awarded to the combination OpenIJ,
consisting of BAM-PGGM, Volker Wessels and DIF. Design of
the lock started in September 2015 and construction in 2016.
Functioning and stability of the Noordersluis and
Middensluis
The realization of this large lock in the lock complex forms a
risk for the stability of the Noordersluis and Middensluis. The
lack of space in the complex means the construction site will be
very close to these existing locks.
The lock complex has a complicated soil profile due to its
history with liquefactions and major breaches. Rijkswaterstaat
has undertaken extensive ground investigations as part of the
preparation for the project. This resulted in limitations on the
horizontal and vertical deformation at the top of the existing
locks, limitation of vibration of the existing structures and
limits on ground water levels and groundwater pressures near
the existing locks. With the obligations to monitor deformations
and ground water pressures in time, it is possible to construct
the new lock at the prescribed location with a minimum risk of
failure of the existing locks. For example: the horizontal displa-
cement of the existing locks is limited to 10 - 30 mm. This is
feasible with the use of diaphragm walls.
ir. Paul Wernsen
BAM infraconsult
ir. Leon Lous
Volker Infradesign
1
Impression of th new lock and existing Noordersluis (to the right)credits: ZUS2 Overview of the new lock situated between the existing Noordersluis en Middensluis
3 Typical cross section lock chamber.
2 Noordzeekanaal
Amsterdam
landside
lock head
seaside
seaside lock head
seaside
Fuikwand
Tussendam Noordersluis
545 m
new lock 70 m
Middensluis
+ 5.000
70 000
39 750
-31.500 construction
existing
Noordersluis
GEWI-anchor
GI-anchor
drainage
lock bottom (0,8 m)diaphragm wall floating frame poured up wal lock plate
-31.500
+ 8.850
+ 5.000
+ 0.000 m 11.5
-17.850
3z
3n
3
3
World?s largest sea lock 3 2017
World's largest sea lock 3 2017 66
thema
4 Digging of the diaphragm wallscredits: Ko van Leeuwen5 Installation of door chambers by the pneumatic caisson method
OpenIJ has carried out further research in order to determine
the influence of the selected construction methods and validate
the design. Field trials were undertaken to validate the prediction
models used for vibration and settlement. The validation models
make it possible to take effective mitigation measures, which
include decreasing embankment slopes, installing rock layers
and drainage.
The design of the OpenIJ is characterised by a number of
execution methods which were chosen to minimise the impact
on the existing locks. As much as possible, the vibration-free
diaphragm wall method will be applied for the construction of
the chamber walls. The two chambers for the rolling gates are
constructed on ground level and installed using the pneumatic
caisson method. On locations where diaphragm walls are not
possible, sheet piling or combined walls will be necessary.
When the impact on the existing locks is too large, sheet piles
will be applied in a cement-bentonite slot and tubular piles for
a combined wall will be drilled.
Flood defence system
The lock complex in IJmuiden fulfills the function of primary
flood defence. The existing flood defence system and flood
defence formed by the new lock must be assured at all times.
In the preparation phase Rijkswaterstaat has undertaken
research on the requirements for the primary sea defence
system for the new lock, taking into account the possible sea
level rise due to climate change. The most important require-
ment is the retaining height of 8.85 m + NAP for the flood
defences with exception of the sea side lock gate which must
meet a retaining height of at least 7.8 m + NAP. This reduced
retaining height results in an additional volume of waterhazard.
Considering the complete system of flood defence, this additional
volume is limited, because the width of the lock gate is only a
very limited part of the flood defence line. Considering the
local situation, it is checked that the water storage capacity of
the Noordzeekanaal is more than sufficient to deal with this
volume.
Part of the contract of Rijkswaterstaat, amongst other things, is
providing sufficient robustness of the flood defence system.
OpenIJ created this additional robustness by using the flood
defence height of 7.8 m NAP for both the seaside and landside
gates and applying walls along the lock chamber with a retaining
height of 8.85 m NAP. As one gate will always be closed there is
always a closed flood defence, even in the unlikely event that
the seaside gate cannot be closed during a storm surge.
4
5
67
Gate chambers
At the end of 2016, sheet piling and tubes were installed to
create the temporary building pit for the construction site of
the gate chambers. To construct the chambers for the seaside
and landside gates, a dry working level will be created inside
the building pit at 5 metres below the current water level (fig. 5).
At this elevation the cutting edge of the pneumatic caissons will
be build, formed by concrete triangles 2.5 m high. On top of
the cutting edge the 4 m thick floor will be constructed, followed
by the lower section of the up to 7 m thick walls. This first part
of the caisson will be lowered by 5 m by the pneumatic caisson
method. After reaching this depth the second stage of the walls
is constructed and the structure is than lowered 13 m to its
final depth. Use of the pneumatic caisson has the advantage
that a building pit with heavy combined walls, heavy supporting
frames and an anchored underwater concrete floor could be
avoided. By doing so vibrations and noise could be minimized.
The IJmuiden sea lock is one of the so-called Connecting
Europe Faciliting and is partly financed by the EU's CEF
programme. At the moment construction of the lock is in full
swing. The lock should, after a period of testing, be operational
by the end of 2019.
?
Diaphragm wall
Because the new sea lock will be built between the Noordersluis
and Middensluis, a large portion of the Middensluiseiland has
to be removed. This is necessary for the lock itself but also for
the approach channel on the seaward side.
Since the Middensluiseiland is part of the flood defence, a
structure must be built west of the new lock to facilitate the
approach to the new lock as well as to protect the inland against
high water levels. This structure, the so called Fuikwand and
Tussendam (fig. 2), connects the Middensluis with the new
lock. Additional robustness has been provided by the use of
diaphragm walls for this structure.
The Fuikwand is an anchored diaphragm wall and the Tussen-
dam is a coffer dam consisting of a diaphragm wall on the
seaward side and a combined wall at side of Noordzeekanaal. A
diaphragm wall has been selected here in favour of a steel sheet
pile or combined wall because of possible ship collision. This
comprises all types of collisions, including the governing colli-
sion with a bulbous bow. In case of a collision the damage of a
diaphragm wall will be less than that of steel sheet pile or
combined wall. A collision could result in a hole in a sheet pile
or combined wall through which sand from behind the wall
could run away causing damage to the dam.
The construction of the diaphragm walls started in January
2017 (fig 4).
6
6 New sea lock under
construction
credits: Topview Luchtfotografie
World?s largest sea lock 3 2017
Reacties