In extending the existing railway infrastructure from Brussels to Antwerp, a new double track railway is foreseen as a bypass along the railway station in the city of Mechelen. In combination with
this, the station will be extended with an underground parkingbuilding. This car park will be reached by a new tangent road connection between the southern and northern part of the city, which should improve and the accessibility of the railway station and reduce the traffic in the center of Mechelen.
52
thema
Complex railway
bypass
1
Combined bypass railway and tangent road
near the station of Mechelen (Belgium)
In extending the existing railway infrastructure from Brussels to
Antwerp, a new double track railway is foreseen as a bypass along
the railway station in the city of Mechelen. In combination with
this, the station will be extended with an underground parking
building. This car park will be reached by a new tangent road
connection between the southern and northern part of the city,
which should improve and the accessibility of the railway station
and reduce the traffic in the center of Mechelen. The road connection is situated parallel and underneath the
new railway bypass for half of the project (fig. 2). This results in
a combination of heavy concrete road tunnels and railway
viaduct infrastructures in an urban environment. In December
2017 the project will be finished.
The tangent road tunnel
The southern tunnel entrance in the combined road and
railway project consists of different cross sections (fig. 3). The
end of the concrete viaduct of the bypass railway infrastructure
in elevation is the start of the road tunnel for a double 2-lane
road infrastructure. An optimization is achieved by bundling of
thema
Complex railway bypass 3 2017
53
Bestaand terrein
Aanvulling
tracks
existing terrain prole
Colomalaan
sliding door every 65 m
railway bypass
groundwater level existing tracks
tangent road
tangent road parking Colomalaan railway bypass
existing tracks
tangent road
tracks
BESTAANDE
L25-B
Bestaand terrein
TANGENT
Aanvulling
Uitgraving
tracks existing tracks
tangent roadexisting terrain prole
D-walls
supplement
excavation
railway bypass
groundwater level
both infrastructures and limiting the required space. The
tunnel structure consists of diaphragm walls of which the outer
wall is a temporary retaining wall to the existing railway infra-
structure (fig. 3c). After construction of the diaphragm walls,
the tunnel deck plate will be constructed after which the tunnel
can be excavated and finally the tunnel floor can be executed.
In the deepest part, the tunnel structure is fully situated under -
neath the ground water level.
One particular structure near the tunnel entrance is the railway
bridge over the Jubellaan. The railway bridge is a continuous
bridge over three spans (28 m ? 44 m ? 28 m) with the super -
structure weighing 2521 tons. The cross section consist of a Bart De Pauw
TUC RAIL
1 View on the finished rail viaduct over the
Leuvense Steenweg
2 Plan view of the road connection project
(yellow: full road connection, red: tunnel
part, purple: additional entrance to tunnel
and parking building)
3 Cross sections of the tangent road tunnel
entrance in the southern part of the project
2
3a
3b
3c
Complex railway bypass 3 2017
Complex railway bypass 3 2017 54
L25N
L25
bicycle path niv +11.50m TAW
groundwater level groundwater level
solimix (55 cm thickness) solimix (55 cm thickness) existing terrain profile
L25N-AL25N-B
L25N-AL25N-B new terrain profile
L25N
L25
100
902 1013.7
1240.4
1341.3
(11.13)
(7.09)(21.34)
L25N-A
L25N-B
L25N-A
thema
5 4
6a
6b
55
ing structure for the existing railway infrastructure as well as a
viaduct structure for the bypass railway infrastructure.
Another structure near the tunnel entrance is the railway
bridge over the Leuvense Steenweg. The bridge section is an
extension of only the railway section of the entrance (fig. 3a).
The railway bridge is a continuous bridge over three spans
(31.5 m ? 33.5 m ? 31.5 m) with the superstructure weighing
2750 tons. The cross section consists of a U-shaped section
with outer main beams and a hollow concrete deck. Both
main girders and the deck are reinforced with unbounded
post-tensioning cables (photo 8). In contrast to the other
railway viaduct over the Jubellaan, this bridge is cast on site,
immediately at its final position (photo 1).
Skew post-tensioned concrete railway bridges
At both sides of the project to arrive to the tunnel entrances,
the tangent road needs to cross the existing railway consisting
of four tracks approaching the station under a skew angle of
45°. This is achieved by four similar skew post-tensioned
concrete continuous slab railway bridges (photo 9a and 9b).
The cross sections of the solid slab bridges with a width of 14 m
are slightly curved and have side girders. The continuous slabs
hollow concrete cross section with post-tensioning cables in
the inner ribs and external post-tensioning cables in the inner
hollow parts. The cross section has variable height. Special
friction tests have been performed on a test beam on site since
no ATAG certification was available for the type of bonded
post tensioning cables that were used. The bridge was erected
some 250 m from its final position. During a weekend closure
of the Jubellaan, the bridge was transported to its final position
by means of a SPMT (Self Propelled Modular Transporter).
Afterwards, jacking was performed in lifting and redistributing
the total weight of the bridge over the pier structure and abut-
ments (photo 4).
In the northern tunnel part of the tangent road project, road
and railway alignment is split again smoothly (photo 5 and fig.
6). For architectural reasons, the roof of the tunnel opens partly
and carries a green roof. When additional lanes of the tangent
road structure appear towards the crossing with the existing
road, the Leuvense Steenweg, the roof structure is made skew
(fig. 6b). Soil mix retaining walls are made in limiting the
excavation since the ground is contaminated with a historic
remnant. The base of the tunnel entrance structure is situated
underneath groundwater level. The rest of the tunnel structure
consists of reinforced concrete. The structure is partly a retain-
4
View on the railway
viaduct crossing the
Jubellaan near the tunnel
entrance
5 View on the northern
tunnel entrance during
construction
6 Cross sections of the
tangent road tunnel
entrance in the northern
part of the project
7 View on the tangent road
tunnel entrance in the
northern part of the
project
8 View on the rail viaduct over
the Leuvense Steenweg
under construction at the
northern tunnel entrance
9 View and cross section of
the skew post-tensioned
concrete railway slab
bridges
7 8
9a 9b
Complex railway bypass 3 2017
56
L25 L25N
low sound screenLeuve-Dijle canal
275
1140
275
175
645 645
(NIV.: + 10.058)
(NIV.: + 6.000) (NIV.: + 6.000)
(NIV.: + 10.058)
tangent road
ground level ground level
L25N
L25
have a double span of about 25 m and a total length of 50 m.
The influence of the skew angle is analyzed and the post-
tensioning in the edge beams has been optimized. The total
railway line breaks were limited to four weekends per bridge.
In the first three weekends the preparatory works are carried
out in making the foundation piles and the sheet piling of the
abutments and piers and in installing temporary steel bridge
decks under which the abutments can be built. In the mean-
time, the superstructure is constructed and prestressed on a
building scaffold 200 m from its final position. During the last
line break, the bridge has to be transported to its final position.
The steel bridge crossing the 'Leuvense Vaart'
A particular spot in the tunnel alignment is the crossing with
the 'Leuvense Vaart'. This crossing with the canal of both road
and railway infrastructure is located near the existing historical
steel Vierendeel bridges. The crossing of the bypass railway
happens above the canal, while the tangent road infrastructure
crosses the canal underneath being the deepest part of the
tunnel (fig. 10). An important design criterion is keeping the
full view of the historic Vierendeel bridges. A final design was
developed in using an integral steel portal bridge.
The bridge consists of two lateral main girders having variable
rectangular sections and is designed as an integral structure
without bearings. The span is about 65 m, which is 5 m more than
the arch Vierendeel bridges and has a reversed curvature near to
the arch springs of the Vierendeel bridges (photo 11). The inverse
curvature of the new bridge only makes sense if the abutments are
fully integrated in the supporting tunnel structure underneath.
10 Cross section at mid span
containing existing and
new railway infrastructure
and a new road tunnel
11 Artist's impression of the
final design with steel
portal structure
12 Front view and cross
section of the total project
with tunnel and bridge
13, 14 Fixations of the steel
structure with post-
tensioning bars
10
12b
12a
thema
Complex railway bypass 3 2017
57
Conclusion
In completing the high speed railway network in Belgium,
a new railway bypass between Brussels and Antwerp will
be constructed in the city of Mechelen. This includes the
extension of the existing railway station of Mechelen. The
optimal bundling of both railway and tangent road makes it a
complex situation. As a railway infrastructure, these structures
are exceptional in the use of post tensioning concrete as well as
in its design and shape.
?
?
REFERENCES
1 Pauw, B. de, Van Bogaert, Ph. (2011). The design of an integral steel
railway bridge in Mechelen (Belgium). Proc. Eurosteel 2011, Budapest,
Hungary.
2 Pauw, B. de, (2014). The new combined road and railway infrastruc-
ture crossing the canal 'Leuvense Vaart' in bypass of the railway
station of Mechelen (Belgium). Proc. Congress AFTES Lyon 2014,
Lyon, France.
The foundations of the new integral railway bridge consist of
reinforced concrete slabs spreading the reaction forces to
several diaphragm walls which are part of the tunnel structure.
This is done by a complex concrete structure with internal
concrete shells transferring the forces from the main box
girders to the vertical walls of the tunnel (the two outer and the
inner wall).
The both outer diaphragm walls are not only temporary retaining
walls for construction of the tunnel, but also the final vertical
deep foundations of the total structure. A particular concern in
the design of the bridge is the abutment stiffness providing the
clamping of the steel superstructure in the concrete foundation.
Therefore, a parametric study by finite element modeling has
been performed (fig. 12 [2]). The steel construction is fixed by
post-tensioning bars diameter 47 mm and 75 mm as well as by
steel dowels on the outer steel webs which are fading into the
concrete abutments. The fixations with post-tensioning bars are
simulated as fixed points at the level of horizontal steel plates
(fig. 13). Photo 14 shows the preparation of the bars during
execution.
11
14
13a
13b
Complex railway bypass 3 2017
Reacties